Target

This construction management project, included the razing of an
existing 90,000-square-foot retail building and extensive off-site
improvements such as road-widening, intersection upgrades and over
1/4 mile of 36" storm-drain piping. The project was further
challenged when owner approvals caused a two-month delay to a nine-month
schedule. The Wrenn team worked with the owner and subcontractors
to expedite the schedule and meet Target's original completion dates.